The machine is good, the setting is not. Cp is high (the process fits inside the tolerance with room to spare) but Cpk is low because it is off-centre. This is fixed by moving the mean, not by buying a new machine.
With n = 10, the control limits sit 3.16 times closer to the centre than the spread of individual parts. A sample average that falls outside the orange limits can correspond to parts that are all within tolerance: the chart warns before scrap is produced. That is what prevention means.
You have had 30 consecutive samples with no point outside the control limits. Production tells you that 3 % of parts are being rejected at final inspection. Is that possible?
Correct. Control limits come from the process itself, not from the drawing. A process can be perfectly predictable and still be centred on a value that does not conform, or simply be too wide. This is quadrant III of the matrix: stable but not capable. The fix is not tighter control, it is a better process. § 10.4 · four-quadrant matrix
Situation 2 of 8
You are designing the control chart the operator will see at the machine. Do you draw the tolerance limits on it?
Correct. If the operator sees the tolerance, they will stop reacting to the control limits and wait until the drawing limit is close. As a rule in this guide (see § 10.3.1): the chart at the line carries only control limits; the tolerance is handled in loops 2 and 3, to decide containment. § 10.3.1 · p. 74
Situation 3 of 8
You have measured 125 parts from a series process and calculated the indices, but nobody has assessed stability with a chart. What are the indices called in your report?
Correct. The arithmetic is exactly the same, but the letter changes what you may claim. C is used only when stability is demonstrated. If it has not been investigated, cannot be investigated, or the process is out of control, it is P. Pm/Pmk is reserved for machine studies. § 7.2 · Table 7-1
Situation 4 of 8
On an x̄/s chart, which of the two plots do you review first?
Correct. The control limit of the averages chart is calculated from σ̂, which comes from the variation chart. If the variation is out of control, the limits on the averages chart are not valid, and assessing it first leads you to false conclusions. First s, correct it, then x̄. § 10.3.3.2 · p. 81
Situation 5 of 8
A value appears in your data that is clearly outside the tolerance. Is it an outlier?
Not that one. How large a value is does not make it an outlier. An outlier is one that does not belong to the population under study: a measurement error, a part measured twice, a setup measurement. And outlier tests only check the fit to a distribution model, so at most they give an indication. It is also not deleted: it is flagged as invalid and the cause is investigated. § 7.6 · p. 36
Situation 6 of 8
You calculate Cwk = 1.85 and Ppk = 0.95 on the same data. What is that difference telling you?
Correct. Cwk uses only the within-subgroup variation, that is, what the machine does at a single instant. Ppk uses the total variation, which includes what moves between subgroups. A large difference means the process jumps from one sample to the next: batch changes, wear, shifts. And note: Cwk is diagnostic, it is not reported. § 7.8.2.5 · p. 43
Situation 7 of 8
How is sample size handled in a final process study?
Correct. The final edition allows adjusted targets with 75 ≤ N < 125 and uses the base target from N = 125. The typical strategy in § 9.2 is 25 subgroups of 5 parts, but it must not be presented as an absolute minimum. Temporal representativeness and the sufficiency of the chart are reviewed separately. § 9.2 and § 9.5 · p. 57, 65–66
Situation 8 of 8
A supplier sends you a report that says only "Cpk = 1.45". What do you ask for before accepting it?
Correct. Without the .G or .Z suffix you do not know which method produced it, and under non-normal distributions the two do not agree. Without proof of stability it cannot be called C. Without the distribution model you do not know whether 1.45 means anything. And without n you cannot judge the confidence interval: a Cpk of 1.45 from 30 parts can have a lower bound below 1.00. ch. 12 · report elements 15–19
7 of 8. Good going.
The basics are there. Review the clauses flagged below and try the calculator in section 06 with your own data.